MUHARRAQ SEWERAGE PROJECT
Dongah Geological Engineering Co. Ltd
We have supplies specialized manpower services for the Micro Tunneling Project for the Muharraq Sewerage Project to M/s Dongah Geological Engineering Co. Ltd , which included highly experienced and skilled Civil Engineers, Land Surveyors, and Welders, Safety Engineers and Technicians.
Aqua Technology Transfer Company W.L.L. has provided manpower and procurement support including:
- Mobilization of skilled manpower including Engineers, Surveyors, Electrician, Welders, HSE Manager and Safety Officers.
- Assisting for importing and exporting Micro Tunneling Equipment’s and Materials.
- Legal Requirements – Assistance and fulfilment.
- ATT was involved in Micro Tunneling works until completing entire project.
- Micro Tunneling Scope of Works includes as follows:
- Preparation and Set-up (TBM and Back-up plants).
- Launching (Initial Driving).
- Main Drive – Pipe Jacking, Slurry pipe / hose installation, hot works, survey
- Reception & Recovery
- Grouting
- Cleaning – Internal and Shafts Bottom
- The Micro-Tunneling works consisted of 3,931 meter length with an inner diameter 1,800 mm.
- Entire drives was completed within 303 days
- Total Man-hours achieved 494,496 without any lost time incident.